Project Description
CTA Milwaukee Blue Line Track Renewal, Chicago, IL
Design/Construction Engineering
Renovation of Elevated Track – Responsible for design and overseeing construction for the traction power system.
Construction Responsibilities include review and response to RFI’s, Shop Drawing Reviews, Cost Estimate Reviews, Change Order Reviews and Installation Oversight.
Project Details
KEY PERSONNEL
Sunish Mathew, P.E.*
AGENCY/OWNER
Chicago Transit Authority (CTA)
PROJECT TYPE
Traction Power/Design & Construction Engineering
PROJECT DURATION
Design: 09/2013-12/2013
Construction: 12/2013-12/2014
*The listed personnel had a key role in completing this project prior to joining Facet team.